Background The on going
work within WG B5.11 – The Introduction of IEC61850 and its Impact on
Protection and Control within Substations indicates the need of specific
definitions on how to perform and evaluate the results of functional tests
of IEC61850 based systems. Such evaluations are beyond the WG B5.11 scope
and time schedule.
Scope
WG B5.32 shall report
on how functional testing shall be performed in IEC61850 based systems. The
report shall cover functional testing from IEDs to overall systems.
Six main areas shall
be focused:
-
Functional
testing of IEC61850 based systems
-
Distributed
application testing
-
Overall system
testing
-
Use of SCL
(Substation Configuration Language) for the testing
-
Functional test
system requirements and definitions
-
Functional
testing considerations to be taken into account in the specification
Conformance (type and
interoperability) testing of IEC61850 based systems (and IEDs) will not be
focused as they are already covered by module 10 of IEC61850. All IEDs will
be assumed to conform to this standard. |
News
| Participants from Brazil, USA, France, Australia, United Kingdom,
Portugal, Canada, Switzerland, Austria, Spain, China, Korea, India, Netherlands |
| Meeting opening by Chairman of SC.B5 |
| Venue of first meeting at
Recife Palace
Hotel |
| Venue of second meeting in Bethlehem, USA |
| Venue of third meeting in Madrid, Spain |
| Venue of fourth meeting in Klaus, Austria |
| Venue of fifth meeting in Paris, France |
| Inclusion of a Reference Term
for the Work Group |
| Inclusion of the
Technical Brochure
Final Draft |
| Inclusion of the
Electra Paper Final Draft |
|